Recommissioning Legacy Substations for Modern Loads: A How-To Guide

By Joe Hamlin 
US Data Center Solutions | April 2, 2025 
📧 info@usdcs.net | 🌐 www.usdatacentersolutions.com 

Executive Summary 

As data center demand surges, developers are revisiting older substations as faster alternatives to greenfield builds. But recommissioning a legacy substation to handle modern, high-density digital loads requires much more than flipping a switch. From relay upgrades to arc flash coordination and transformer diagnostics, this guide outlines how to modernize aging substations for today’s power-hungry infrastructure. 

Why Legacy Substations Are Back in Play 

- New substations can take 24–36 months to commission. 
- Material shortages and utility queues delay new builds. 
- Redeploying substations can shave 12–18 months off timelines. 
- Many legacy substations were built for industrial loads, not AI or hyperscale compute. 

Step 1: Begin with a Full Field Assessment 

Before energizing or upgrading, answer the following: 
- What’s the age, manufacturer, and capacity of each major component? 
- Are as-built drawings accurate and complete? 
- How long has the system been de-energized? 
- Are there visible signs of degradation (leaks, rust, damaged bushings)? 
💡 Pro tip: Assume undocumented changes exist. Legacy gear is often modified in the field without updates to one-lines or relay settings. 

Step 2: Modernize Protection and Controls 

Most substations built before 2005 rely on electromechanical relays. These are outdated, slow, and lack remote logic capabilities. 
🔧 Upgrade to digital relays (e.g., SEL, GE, Siemens) to gain: 
- Precise fault clearing and breaker timing 
- SCADA-ready monitoring and alerts 
- Coordination with new BESS or solar DERs 
📚 Reference: IEEE Std C37.2-2023 

Step 3: Test Everything—Don't Assume It Works 

Even if the gear looks clean, it needs to be tested. Here’s what to run: 
- Transformer Testing: 
  - Doble Power Factor 
  - TTR (Turns Ratio) 
  - SFRA (Sweep Frequency Response) 
  - Oil sampling and DGA (gas-in-oil) 
- Breaker Testing: 
  - Timing and contact resistance 
  - Primary injection if possible 
- Ground Grid Testing: 
  - Continuity and Step/Touch potential 
⚠️ Transformers that sat idle may have internal moisture or coil damage. 

Step 4: Review Fault Levels and Load Growth Potential 

Modern data centers use constant, inductive, and non-linear loads unlike anything these substations were designed for. 
✅ Run: 
- Short-circuit and arc flash studies 
- Breaker clearing coordination 
- Thermal derating checks on transformers and bus duct 

Step 5: Plan Phased Upgrades with Minimal Downtime 

If you’re operating a hybrid or transitional site: 
- Use mobile transformers or modular E-houses for temporary loads 
- Schedule cutovers on nights/weekends 
- Build bypass paths for critical loads 
🛠 Tip: Some operators use staged upgrades—gear on one side while the other stays live, then flip. 

Step 6: Upgrade Physical and Cybersecurity 

Legacy substations were not built for today’s risks. 
🔐 Consider: 
- Relay password protection and firmware updates 
- Firewalls and VLAN segmentation between IT and OT 
- Keypad or biometric entry at doors 
- Security cameras with local + cloud monitoring 
📚 Reference: CISA Cybersecurity Guidelines for Substations (2023) 

Final Thoughts: Don't Just Reuse—Reimagine 

A legacy substation can be an asset, but only if it’s thoroughly tested, modernized, and upgraded for resilience. With today’s high compute loads, even a small oversight in relay coordination or oil testing can lead to catastrophic failure. But with the right team and plan, recommissioning can become your fastest route to power-on. 

Want Help Evaluating or Recommissioning a Substation? 

We offer site walks, one-line reviews, arc flash coordination, and upgrade design for hyperscale, modular, and edge data centers. 
 
📩 Email Joe Hamlin at info@usdcs.net 
🌐 Visit: www.usdatacentersolutions.com 

Previous
Previous

Gain actionable insights about your data center environment.

Next
Next

Revolutionizing Data Center Operations with AI